Put together the plant room doors, just to get the hole closed up. These aren’t pretty by any means – timber frame, cement sheet cladding:

….but they’re solid enough and will get the job done.
Also got some more internal wall-stuffing done, now that the plumbing and electrical is done. The 2nd bedroom is now closed up, and the laundry is basically done as well. I used a sheet of villaboard as the backing for the laundry area:

to make it easier to mount cupboards and tiles, rather than trying to get perfectly flat render to tile over. In theory I can match the render up with the tiles…we’ll see how that goes. 🙂
Other internal walls…..2nd bedroom:


Hallway:
