Winter strikes

Categories Uncategorized

It’s extremely wet in Perth.

Thankfully the house’s first coat is almost complete, so I’ve been able to dispense with the plastic wrapping – probably a good thing, since the wind was starting to tear it all to shreds anyway.

Seemed like a good excuse to do some inside work – we’ve now pretty much finished the internal meshing (at last!). We also cleared out all the recessed rooms of the house – the master and 2nd bedrooms, main bathroom and 2nd toilet – and sealed the floor:

This wasn’t really on my critical path at all, it just made sense to do it now so I can move everything off the ‘presentation’ floor (the living room etc) and seal that.

Leave a Reply

Your email address will not be published. Required fields are marked *